
13/1 North end of the NS Fence. Bill S & Ben F on the auger drilling posts for the 4.2m + 2.4m gate
Click to see more










13/1 First post in at the south end



13/1 Geoff M and David W



13/1 Installing posts for the gate at the centre of the field Should make it easier to retrieve planes A great idea from Ben.





18/1 David W meets with Civilmech (Robert on left, Ryan on right) to finalize the scope of the SEMAC earthwork at MulchjXpress

18/1 David W shows Robert and Ryan the important SEMAC landmarks at MX. This was Civilmech’s third visit

18/1 Checking truck access with Civilmech

18/1 David introduces MX site boss Glen to Civilmech. Importantly a working relationship was immediately established

18/1

18/1 Ryan checks where the nearest non-metered hydrant is located. Water is needed to set the crushed recycled concrete access road

18/1 The work is agreed to start in Feb

20/1 Glen of MX is out slashing gorse. Geoff, Dino and Bill are at MX for the arrival of the second container which is to be the new cookhouse

20/1 Another view of the MX Gorse slasher


20/1 Glen had arranged the MX guys to expect the new container so there were no delays.

20/1 Lowering the container



20/1 The cookhouse has landed.

20/1 Dino and Bill inspect the interior

20/1 The long and short of it

20/1 Dino inspects the secure lock fitting. Don’t lose the key

20/1 Bill prepares to launch a glider

20/1 Rod works on slashing the fence line

28/1 Dino and Geoff at the field checking all is in place for the 31/1 working bee
New 100lit tank delivered by Rob B beside the leaky one

28/1 Dino inspects the newest gate delivered by Brendon on 27/1
There will be a 7m opening at the north end to allow MX slasher through and any emergency vehicles

28/1 New gate is top quality - a great find by JJ

28/1 Looking south towards the south end of the NS runway and showing the work done by Brendon on 27/1 with the Bobcat to prepare grading by Civilmech

28/1 Looking north up the NS runway

28/1 South end of the NS runway

28/1 East end of the EW Runway looking west

28/1 East end of the EW Runway looking west

28/1 West end of the EW runway looking east

28/1 Posts laid out by Brendon in readiness for the 31/1 Working Bee

28/1 Still plenty of posts left for the pits & flight line

31/1 Working Bee to put in all the posts needed for the North South fence to keep the cattle off our future runways.
A hard day’s work but very successful

31/1 Gary, C, David W, Ben F, and Rob Bruin hard at it

31/1 Simon brings in another post
About 70 were installed

31/1 Taking a break are Bill S, Dino T, Simon, Gary C, Vince M, David W and Rob B
Also present were Ben F, the man with the fencing smarts, John A, and Geoff M

31/1 One more hole

31/1 The view at the end of the day
SIMON’s SERMON - JAN 2021
Hi Everyone,
Click on the photo above to see more pics of the progress on the field during January. If the photos appear cut off at the drag in the LHS or RHS of your screen to bring everything into view. If using a mobile just rotate your phone 90 degrees.
Hover your mouse or touch the screen to see photo captions.
Regards,
Simon